Jan 1, 2011

In just three months of extremely choppy external markets, Project Jaguar scored a coup.

As international banks ran scared of taking on emerging market risk it corralled a largely Central American bank group to get cracking on a power project deemed crucial to Guatemala’s future.

Jaguar closed a $350 million 10-year project finance loan at the beginning of April 2010, paying Libor plus 575 basis points. The tenor is longer than expected for Guatemala, where 5-7 years for project finance is more typical.

Jaguar involves construction of a 300 megawatt solid fuel-fired power plant to supply thermal based energy to Guatemala. China Machine New Energy Corporation (CMNE) is the builder. Cabei and Bancolombia were...

To continue reading please take a free trial, subscribe or login below.

Already have an account?


Subscribe now for unlimited access to all current and archive news, data and market analysis. 


Free trial

Take a free two-week trial now for the latest news, data and market analysis.

Free Trial

LatinFinance Events


Will a strong dollar deter investors from LatAm bonds?